SUCCESSFULLY ENERGIZING 110KV AMATA 1 SUBSTATION – PHASE 2, QUANG NINH PROVINCE

28/02/2023 - Người viết: AIT
SUCCESSFULLY ENERGIZING 110KV AMATA 1 SUBSTATION – PHASE 2, QUANG NINH PROVINCE
At 7:36 pm on February 16th, 2023, Advanced Information Technologies Corporation (AIT CORP) and related units successfully energized 110kV Amata 1 Substation – Phase 2, Song Khoai Industrial Park, Song Khoai Commune, Quang Yen Town, Quang Ninh Province.

Located near Hai Phong Port and on the road axis directly connecting to Mong Cai border gate, Song Khoai Industrial Park has basically completed construction of phase 1 with typical projects such as Jinko Solar 1 and 2 Silicon Panel Technology project with a total investment of nearly 900 million USD. With its advantages in geography and transport network, the Industrial Park has contributed to creating the driving force for the development of Quang Yen coastal economic zone and is expected to continue to attract investment waves in Quang Ninh province in the future. Therefore, in order to ensure power supply for business activities, avoid production interruptions and reduce losses for businesses in the Industrial Park, the completion and energization of 110kV Amata 1 substation - phase 2 is an urgent requirement. 

With the trust of the Investor – Amata Halong City Joint Stock Company, AIT CORP had the opportunity to participate and accompany throughout the 2 phases of the 110kV Amata 1 substation, in which: 

Phase 1: AITCORP is the representative of AIT-Thanh Vinh Joint Venture for the package: Surveying, Engineering, Procurement and Construction of 110kV Amata 1 substation with capacity of 1x63MVA, officially put into operation from November 15th, 2021. 

Phase 2: AITCORP plays the role of General Contractor of Engineering, Procurement and Construction for 110kV Amata 1 substation with 2 transformers and capacity of 2x63MVA. Specifically: 

The T2 transformer has been successfully energized and put into use. When in operation, the T2 transformer will reduce the load on the T1 transformer, improving the reliability of power supply for Song Khoai Industrial Park. 

The 110kV side is added two 110kV feeders for T2 and T3 transformers. 

The 22kV side is added the following 22kV distribution cabinets: 02 total cabinets for circuit breakers, 10 cabinets for outgoing circuit breakers, 02 cabinets for measurement, 01 cabinets for self-using transformers, 02 cabinets for segmentation disconnection switch and 02 cabinets for segment circuit breaker. 

Along with the success of the project, AIT CORP has had a good start for the year of the Rabbit year 2023, continuing to set its foot on the path of developing Vietnam's electricity grid.  

Sincerely thank to Amata Halong City Joint Stock Company, Quang Ninh Power Company and related units for coordinating and helping AIT CORP to complete the project.

Congratulations to the staff of AIT CORP! 

 

Image: Outdoor primary equipments 

 

Image: T1 Transformer provided by AIT CORP in Phase 1 

 

Image: T2 Transformer 

 

Image: AIT GROUP staff check the status of equipment before energizing 

 

Image: Fire prevention and fighting units are ready to prevent incidents when energizing 

 

Image: Electrical cabinets provided by AIT 

 

Image: The control screen of the computer system at the substation carried out by EGRID - a member unit of AIT GROUP 

 

Image: AIT GROUP staff with representative of the Investor and related units cooperate in energizing 

TVQuản trị viênQuản trị viên

Xin chào quý khách. Quý khách hãy để lại bình luận, chúng tôi sẽ phản hồi sớm

Trả lời.
Thông tin người gửi
Bình Luận
Nhấn vào đây để đánh giá
Thông tin người gửi
2.80548 sec| 803.883 kb