SUCCESSFUL COMMISSIONING OF THE 110KV VINH LOC SUBSTATION IN THANH HOA, AIT GROUP CONTINUES ITS STREAK OF ENERGIZED PROJECTS

29/05/2024 - Author: AIT
SUCCESSFUL COMMISSIONING OF THE 110KV VINH LOC SUBSTATION IN THANH HOA, AIT GROUP CONTINUES ITS STREAK OF ENERGIZED PROJECTS
In celebration of the upcoming 95th anniversary of the Vietnam Trade Union (July 28, 1929 – July 28, 2024), the 70th anniversary of the Vietnam Electricity Traditional Day (December 21, 1954 – December 21, 2024), and the 55th anniversary of the Northern Power Corporation (October 6, 1969 – October 6, 2024), AIT Group and partner contractors successfully energized and commissioned the 110kV Vinh Loc - Thanh Hoa Substation on May 27, 2024.

Overview of the 110kV Vinh Loc – Thanh Hoa Substation

The Vinh Loc 110kV Transmission Line and Substation project, funded by the Northern Power Project Management Board - Northern Power Corporation, commenced in September 2022. As a strategic infrastructure initiative within Thanh Hoa province’s 2021–2025 development plan, the project addresses the region’s rapidly growing electricity demand, which is forecasted to increase by approximately 15% annually. The scope of work includes the construction of a 6.315-kilometer double-circuit 110kV transmission line utilizing ACSR-300mm² conductors, and a new 110kV substation designed to accommodate two power transformers. In this phase, one 40MVA 110/35/22kV transformer has been installed and commissioned

Substation Yard – 110kV Vinh Loc – Thanh Hoa Substation

Leveraging its proven expertise in project execution nationwide, AIT Group was once again entrusted by the Northern Power Project Management Board to supply, transport, and install equipment for the 110kV substation. The facility meets modern operational standards, functioning as an unmanned substation with remote monitoring and control capabilities seamlessly integrated into Remote Control Center.

Transformer at the 110kV Vinh Loc – Thanh Hoa Substation

Cabinets and Equipment Supplied by AIT Group

Closely adhering to the directives of the Thanh Hoa Provincial People's Committee and the Northern Power Corporation, AIT Group developed a detailed execution plan, mobilized resources, and ensured strict adherence to quality and timeline requirements. Through tireless efforts and determination, AIT Group engineers and employees, in coordination with project partners, successfully energized the substation at 5:10 AM on May 27, 2024.

The 110kV Vinh Loc – Thanh Hoa Substation prior to energization

The 110kV Vinh Loc – Thanh Hoa Substation successfully energized on May 27, 2024

As a vital piece of infrastructure for Thanh Hoa’s power transmission network and industrial expansion—particularly in the Vinh Loc area—the 110kV Vinh Loc Substation is expected to significantly support industrial growth, attract investment, improve the local business, and accelerate the province’s industrialization and modernization efforts, thereby enhancing the overall quality of life for residents.

The 110kV Vinh Loc – Thanh Hoa Substation in operation

Building on the successful commissioning of the Vinh Loc Substation, AIT Group reaffirms its commitment to collaborating on future substations and infrastructure projects nationwide, further advancing its mission to contribute to socio-economic development across communities throughout Vietnam.