SUCCESSFUL COMPLETION OF CAPACITOR BANK INSTALLATION AT THREE PHU THO SUBSTATIONS - FEBRUARY 2025

05/03/2025 - Author: AIT
SUCCESSFUL COMPLETION OF CAPACITOR BANK INSTALLATION AT THREE PHU THO SUBSTATIONS - FEBRUARY 2025
At the end of February, the Capacitor bank installation project at Three 110kV Substations—Thanh Thuy, Tam Nong, and Thuy Van—was successfully inspected, energized, and put into operation on schedule with AIT Group and partnering contractors determination and coordination.

Overview of Capacitor Bank Project at 110kV Substations: Thanh Thuy – Tam Nong – Thuy Van, Phu Tho

Commencing in November 2024, the installation of capacitor banks on the medium-voltage busbars at three 110kV substations Thanh Thuy – Tam Nong – Thuy Van served as the critical initiative, with Phu Tho Power Company – a branch of the Northern Power Corporation – acting as the investor’s representative. On the momentum of its early 2025 achievements, AIT Group was entrusted with the role of contractor for equipment procurement and installation across all three substations. The company successfully delivered safe and seamless integration of the capacitor systems, fully complying with all technical specifications and quality standards.

Equipment supplied and installed by AIT Group

Equipment supplied and installed by AIT Group

Driven by a high level of determination and a strong commitment to the project timeline, AIT Group engineers and employees, alongside partnering contractors, mobilized resources and maintained continuous operations—even through the Lunar New Year holidays—to ensure on-time key commissioning milestones, included: Thanh Thuy 110kV Substation – February 20, 2025; Tam Nong 110kV Substation – February 24, 2025; Thuy Van 110kV Substation – February 27, 2025.

Capacitor Banks at Thanh Thuy – Tam Nong – Thuy Van 110kV Substations Prior to Commissioning

Once operational, the project will enhance the safety and reliability of power supply at the three 110kV substations—Thanh Thuy, Tam Nong, and Thuy Van—meeting the electricity demands of critical loads in these districts of Phu Tho Province. It will also help improve grid stability, reduce power and energy losses, boost operational efficiency, and contribute to local economic development.

Tụ bù 03 TBA 110kV Thanh Thủy – Tam Nông – Thụy Vân thành công về đích tháng 2/2025

The successful, on-schedule completion of this project once again reflects AIT Group’s unwavering commitment to integrity, execution excellence, and uncompromising quality. This achievement reinforces our role as a trusted partner in delivering impactful infrastructure and contributes to shared success with partners and localities nationwide in advancing economic development./.