AIT GROUP SUCCESSFULLY INSTALLS AND ENERGIZES TRANSFORMER T2 AT 110KV NAM SON – HAP LINH SUBSTATION, BAC NINH
19/12/2024
On December 14, 2024, the project for installing Transformer T2 at the 110kV Nam Son – Hap Linh Substation in Bac Ninh was officially accepted and successfully energized by AIT Group in coordination with other contractors, contributing to enhancing the...
SUCCESSFUL ENERGIZATION OF 110KV HOANG HOA 2 SUBSTATION – AIT GROUP MOVES TOWARD ACHIEVING 2024 GOALS
11/11/2024
On October 31, 2024, the 110kV Hoang Hoa 2 Substation was successfully energized and safely put into operation. As a grade II energy project, category B, with a total investment of over VND 150 billion, the project was jointly implemented by AIT Group and relevant contractors.
View more
AIT GROUP SUCCESSFULLY ENERGIZES AND PUTS INTO OPERATION DINH QUAN 220KV SUBSTATION
01/11/2024
In pursuit of its 2024 strategic goals and in celebration of AIT Group’s 21st anniversary (December 1, 2003 – December 1, 2024), AIT Group and its partner contractors have officially energized and commissioned the Dinh Quan 220kV Substation. This project will help meet the increasing electricity demand in Dong Nai...
View more
CONTINUING TOWARD 2024 TARGETS, AIT GROUP SUCCESSFULLY ENERGIZES THE 220 KV SUBSTATION AT NGHI SON ECONOMIC ZONE
31/10/2024
On 27 October 2024, the 220 kV Nghi Son Economic Zone Substation was successfully accepted, energized, and placed into safe operation. Thanks to the unwavering resolve of AIT Group and partner contractors, the project was completed four days ahead of the schedule set by the Party Committee of Vietnam Electricity...
View more
CONTINUING TO MEET Q3/2024 TARGETS, AIT GROUP SUCCESSFULLY ENERGIZES 110KV QUY NHON PORT SUBSTATION
01/10/2024
On September 29, 2024, the 110kV Quy Nhon Port Substation was officially energized and successfully put into safe and reliable operation, enhancing the stability of electricity supply and meeting the increasing power demand of the Quy Nhon Port area.