News

COLLABORATING WITH LEGO MANUFACTURING VIETNAM, AIT GROUP SUCCESSFULLY ENERGIZES 110KV SUBSTATION AT LEGO FACTORY

COLLABORATING WITH LEGO MANUFACTURING VIETNAM, AIT GROUP SUCCESSFULLY ENERGIZES 110KV SUBSTATION AT LEGO FACTORY

27/03/2024

On March 25, 2024, the 110kV Substation Project at the LEGO Factory, located in the Vietnam – Singapore III Industrial Park, Binh Duong, was officially energized and put into operation. The project is invested by LEGO Manufacturing Vietnam Co., Ltd.,...

SUCCESSFULLY ENERGIZED AND PUT INTO OPERATION THE 110KV YEN CHAU SUBSTATION

SUCCESSFULLY ENERGIZED AND PUT INTO OPERATION THE 110KV YEN CHAU SUBSTATION

27/12/2023
On December 21, 2023, the 110kV Yen Chau transmission line and substation project in Sap Vat Commune, Yen Chau District, Son La Province was successfully energized and commissioned. AIT Group was responsible for the supply, transportation, and installation of all primary and secondary equipment, communication systems, and SCADA for the...
View more
SUCCESSFULLY ENERGIZED THE 110KV LY THUONG KIET 2 SUBSTATION – HUNG YEN.

SUCCESSFULLY ENERGIZED THE 110KV LY THUONG KIET 2 SUBSTATION – HUNG YEN.

26/12/2023
On December 24, 2023, the 110kV Ly Thuong Kiet 2 Substation in Xuan Truc Commune, An Thi District, Hung Yen Province was successfully energized and commissioned. The project was led by Hung Yen Power Company, a subsidiary of Northern Power Corporation.
View more
SUCCESSFUL ENERGIZATION AND COMMISSIONING OF THE DONG BINH 110KV SUBSTATION

SUCCESSFUL ENERGIZATION AND COMMISSIONING OF THE DONG BINH 110KV SUBSTATION

22/12/2023
On December 18, 2023, the Dong Binh 110 kV substation was officially accepted and energized. AIT Group served as the contractor for the supply and installation of the 110 kV substation equipment and the SCADA information system for this project.
View more
SUCCESSFUL ENERGIZATION OF 4 EXTENDED BAYS AT THE 500KV VUNG ANG SUBSTATION UNDER THE VUNG ANG II THERMAL POWER PLANT PROJECT

SUCCESSFUL ENERGIZATION OF 4 EXTENDED BAYS AT THE 500KV VUNG ANG SUBSTATION UNDER THE VUNG ANG II THERMAL POWER PLANT PROJECT

21/12/2023
On the afternoon of December 17, 2023, four extended bays at the 500kV Vung Ang Substation were officially accepted and successfully energized. The project, invested by Vung Ang II Thermal Power LLC (VAPCO), is implemented by AIT Group, partnering contractors and related parties.
View more
0.05487 sec| 725.07 kb