SUCCESSFUL COMMISSIONING OF THE 2ND 220KV TRANSFORMER – THÁI THỤY 220KV SUBSTATION, AIT GROUP CONTINUES TO CLOSE OUT APRIL 2024 PROJECTS

SUCCESSFUL COMMISSIONING OF THE 2ND 220KV TRANSFORMER – THÁI THỤY 220KV SUBSTATION, AIT GROUP CONTINUES TO CLOSE OUT APRIL 2024 PROJECTS

28/04/2024
On April 27, 2024, the project to install the second 220 kV transformer at Thai Thuy 220 kV Substation was officially accepted and successfully energized. The project was carried out by the National Power Transmission Project Management Board (NPTPMB), AIT Group, and associated contractors in Thai Binh Province
View more
FOLLOWING A SERIES OF APRIL COMPLETIONS, AIT GROUP SUCCESSFULLY ENERGIZES 110KV VAN TRUNG 2 SUBSTATION

FOLLOWING A SERIES OF APRIL COMPLETIONS, AIT GROUP SUCCESSFULLY ENERGIZES 110KV VAN TRUNG 2 SUBSTATION

27/04/2024
As part of a series of nationwide achievements celebrating the 49th anniversary of national reunification and the 70th anniversary of the Dien Bien Phu Victory, AIT Group has successfully energized several substations across Vietnam. Among them, the 110kV Van Trung 2 Substation in Bac Giang was officially energized on April...
View more
AIT GROUP - MOBIFONE COLLABORATION FOR INSTALLING CENTRALIZED UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM FOR MOBIFONE YEN HOA BUILDING

AIT GROUP - MOBIFONE COLLABORATION FOR INSTALLING CENTRALIZED UNINTERRUPTIBLE POWER SUPPLY (UPS) SYSTEM FOR MOBIFONE YEN HOA BUILDING

26/04/2024
AIT Group, marking a successful collaboration with MobiFone Corporation, has completed the installation of a centralized UPS (Uninterruptible Power Supply) system at the MobiFone Yen Hoa Building
View more
SUCCESSFUL ENERGIZATION AND COMMISSIONING OF 110KV NÀ PHẶC SUBSTATION

SUCCESSFUL ENERGIZATION AND COMMISSIONING OF 110KV NÀ PHẶC SUBSTATION

04/04/2024
Following a series of successful project completions in Q1/2024, the 110kV Nà Phặc Substation, located in Ngân Sơn District, Bắc Kạn Province, was officially energized and put into operation on March 29, 2024. The project is owned by the Power Development Project Management Board, with AIT Group and other contractors...